231) What is the minimum height of an exit door?

Hint2015 IFC Section 1010.1.1

232) A door for a business occupancy opens into the room (23 person occupancy). Is this a problem?

Hint2015 IFC 1010.1.2.1

233) A door was recently installed in ECF. During an inspection, you discover that it takes 18 lbs to release the door latch to open the door. Is this a problem?

Hint2015 IFC 1010.1.3

234) What is the maximum force allowed for starting a door to open from its closed position?

Hint2015 IFC 1010.1.3

235) You are performing a final inspection of a new building before the building department will issue a certificate of occupancy. You notice that one of the exterior swinging doors has a threshold that is 3/4 in above the landing. What do you do?

Hint2015 IFC 1010.1.7

236) A door knob is installed at 33 in above the finished floor. Is this a problem?

Hint2015 IFC 1010.1.9.2

237) During off-shift times, the security organization wants to create a timed delay system so they have time to get focused and assess the scene. This means that egressing personnel will have to wait 14 seconds after badging out of a turnstile protected egress path before an electrical-mechanical latch releases for any door leaving the building. Security is asking you if this is okay. What is your response?

Hint2015 IFC Section 1010.1.9.7.4

238) A government facilities oversite group that regulates your DOE site asks you if panic hardware is required for a room in a business occupancy that seats about 20 people. What do you say?

Hint2015 IFC Section 1010.1.10

239) A Switch Gear Building has its south door on a security required electrical mechanical latch that requires a button to be pressed prior to activating the panic hardware to egress. Is this a problem?

Hint2015 IFC 1010.1.10, Chapter 2 definition for Panic Hardware

240) You are performing an inspection on a new building and discover that a stairway is 36 in wide that goes up to an area that serves an occupant load of 40 people. Is this a problem

Hint2015 IFC Section 1011.2 Exception 1)