2021 ICC Commercial Mechanical Inspector Quiz 5


Home

1) What is the largest soft annealed copper tubing that is allowed for use in field-assembled refrigerant systems? (1,107.4, T1,107.4 Footnote a)

2) Exposed refrigerant piping installed in open spaces that afford passage shall be not less than how high above the finished floor? (1,109.2.1)

3) Refrigerant piping shall not be installed in which of the following locations? (??)

4) Refrigerating piping fittings that will reach a surface temperature below the dew point of the surrounding air where condensation can cause a safety hazard shall be? (1,109.7)

5) Refrigeration systems with more than 6.6 pounds of refrigerant shall require stop valves at which of the following locations? (1,109.8.1)

6) Stop valves installed on copper tubing shall require separate supports if the piping is what size? (1,109.8.3)

7) Pressure testing refrigeration piping shall never use what gas? (??)

8) Steel hydronic piping shall conform to which standard? (T1,202.4)

9) Cut pipe used for hydronic piping shall be? (1,203.2)

10) Pipe joint compound applied to hydronic piping shall only be applied to? (1,203.3.5)

11) The insulation on hydronic piping installed in buildings shall have a maximum flame spread index of? (1,204.1)

12) Openings for hydronic pipe penetrations through concrete elements shall be? (1,206.4)

13) Hydronic piping shall be installed to prevent all of the following, except? (1,206.9)

14) The flash point of transfer fluid in a hydronic piping system shall be not less than? (1,207.1)

15) Hydronic piping systems shall be tested hydrostatically at one and one-half times the maximum system design pressure, but not less than 100 PSI. The duration of each test shall be not less than what time duration? (1,208.1)

16) Embedded hydronic piping is permitted to be all of the following materials except? (1,209.1)

17) Embeded hydronic piping is required to be rated at 100 PSI at what temperature? (1,209.1)

18) Piping to be embedded in concrete shall be pressure tested prior to pouring concrete and the operating pressure shall be maintained? (1,209.2)

19) Embedded steel hydronic piping joints shall be? (1,209.3.1)

20) Hydronic piping in a ground-source heat pump piping system having an external surface temperature exceeding 250 degrees F shall have a minimum clearance of what distance from combustible materials? (1,210.8.3)

21) Nonmetallic piping for fuel oil piping and storage shall only be used? (1,302.4)

22) Joints between diAerent piping materials used for fuel oil piping shall be made with approved? (1,303.1.1)

23) The minimum size of a fuel oil supply line shall be? (1,305.1)

24) Copper tubing used for fuel oil systems shall have a minimum wall thickness of? (1,305.1)

25) A fill pipe for a fuel oil system shall terminate outside of a building at a point not less than how far from any building opening at the same or lower level? (1,305.6)

26) Potable water supplies to solar systems shall be protected against? (1,401.2)

27) Solar thermal system components containing pressurized fluid shall be protected against pressures and temperatures exceeding design limitations by using? (1,402.3)

28) Solar thermal equipment exposed to vehicular traffic shall be installed not less than how far above the finished floor? (1,402.6)

29) Roofing mounted solar collectors that also serve as a roof covering shall conform to the requirements for roofing as specified in the IBC unless what solar collector covers are used? (1,402.8.1.3 Exception)

30) Ducts used in solar heating and cooling systems shall be constructed an installed with an exposed surface temperature limited to? (1,402.8.2)

31) Liquid single-phase solar energy systems shall be equipped with? (1,402.8.7)

32) A flammable liquid shall be used as a heat transfer for solar thermal systems only when? (1,403.5)

33) Factor built solar thermal collectors shall bear a label showing all of the following except? (1,404.1)